Grandview's Two-Year Detour Just Ended. Here's What's Actually Different Now.

September 10, 2026

For more than a year, getting from one side of Edina's Grandview District to the other meant a detour down Eden Avenue, a workaround so routine that longtime residents stopped thinking of it as temporary. Then, on June 26, Vernon Avenue reopened to traffic for the first time since April 2025, and the shortcut that had defined daily errands in Grandview simply stopped being necessary.

That is the easy part of the story, the part every neighborhood newsletter already covered. The part worth sitting with is what actually got rebuilt underneath the relief of a reopened road, and why the timeline slipped the way it did. The interchange that reopened this summer is not the same interchange that closed last spring. It was redesigned, and the redesign changes how people move through this specific corner of Edina on foot in a way that outlasts the ribbon-cutting.

What Actually Got Rebuilt

The old Vernon Avenue and Highway 100 interchange had accumulated six separate access ramps feeding four different streets, a tangle that the city itself described as a significant barrier for anyone trying to walk through the district. The $28 million project, a joint effort between the City of Edina, Hennepin County and MnDOT, replaced that tangle with a standard tight diamond interchange and removed the redundant ramps entirely.

The sidewalks changed too, and this is the detail that will matter more to daily life than the ramp geometry. The old sidewalks were narrow and sat close to fast-moving traffic. The new ones are ten feet wide, with ADA-compliant pedestrian ramps, refuge islands at the crossings and traffic signals with audible crosswalks. Homes in the Sunnyslope neighborhood got a new noise wall as part of the same project, built to cut down on traffic noise for residents nearby.

None of that was optional restoration. It was a decision to make Grandview more walkable than it was before construction ever started, and it is now permanent.

The Real Delay Wasn't Concrete

Most of the heavy lifting finished on schedule. The new bridge over Highway 100 reopened back on November 15, 2025, restoring the bigger of the two river crossings months before most residents expected the whole project to wrap. The second structure, the Vernon Avenue bridge over the CPKC railroad, is what pushed the timeline into the following summer.

The holdup wasn't weather or a contractor falling behind. Crews doing utility work in the railroad right-of-way found a buried power line that nobody had accounted for. Xcel Energy needed a permit from the railroad to relocate it, which it secured in mid-September 2025, and the actual relocation work happened in early October. Only after that could the bridge work resume in earnest.

Date Milestone
April 2025 Interchange project begins
Nov. 15, 2025 Highway 100 bridge reopens
June 25, 2026 Ribbon-cutting on the new Vernon Avenue bridge
June 26, 2026 Vernon Avenue reopens to traffic

City Engineer Chad Millner said as much in one of the project's spring updates: "We look forward to completing the project soon and reopening Vernon Avenue to traffic in late June." The ribbon-cutting itself happened on the new bridge deck, with remarks from Mayor Jim Hovland and Millner, followed by refreshments at Davanni's on Gus Young Lane. Attendees were directed to park in the Grandview Parking Ramp at 5101 Vernon Ave, a detail that only matters if you were actually there, which is exactly the point. This wasn't a press release event. It was a neighborhood one.

During the first stretch of construction, the city ran something called the Worth the Detour Passport, a stamp program that rewarded people for continuing to shop and eat at businesses in Grandview and 50th & France while the roads were torn up. It ran through mid-November 2025, timed to end right as the Highway 100 bridge reopened, which tells you something about how long the city expected that first phase of disruption to actually hurt foot traffic.

Two Different "New Restaurant" Stories

If you've heard that a Jester Concepts restaurant is coming to Grandview, you're both right and behind. Starling, the company's first suburban location, already opened in the district back in May 2024, occupying the ground floor of the Maison Green apartments on Eden Avenue in the former Perkins space. It has been open for more than two years now.

The restaurant people are actually asking about lately is a different one. Hempel Real Estate, working with St. Louis Park-based Monarch Development Partners and Jester Concepts again, announced plans in August 2025 for a three-acre mixed-use redevelopment at the southeast corner of 50th Street and Highway 100, the parcel long used for public works storage. The preliminary plan calls for 38 townhomes and 32 condo units, all owner-occupied, plus green space and a restaurant anchor that Jester had not yet named. At the time, developers were targeting summer 2026 for groundbreaking. Whether that timeline held is the kind of thing you find out by walking past the site, not by reading a year-old press release, so it's worth keeping an eye on this fall now that the season it was pegged to has come and gone.

What's Actually Open This Weekend

None of this happens in isolation from the rest of the city's calendar. The 22nd annual Edina Fall Into the Arts Festival runs Saturday and Sunday, September 12 and 13, at Centennial Lakes Park on France Avenue, several miles from Grandview on the other side of the city. Around 250 artists will set up across two days, alongside food vendors, with proceeds benefiting the Edina First Responders Fund. It's free, it's been running for more than two decades, and it draws crowds from across Edina rather than just the immediate neighborhood.

The festival and the interchange aren't connected by geography. But they're connected by timing, and that timing says something about this particular September. This is the first fall since construction began that a resident can drive across town to Centennial Lakes without factoring in a Grandview detour, without checking whether Vernon Avenue is open that week, without the low-grade planning that construction seasons require. That kind of freedom from mental overhead doesn't show up in any press release, but it's the thing that actually changes how a place feels to live in.

What This Means If You're Watching Grandview

The headline version of this story is that a road reopened. The more useful version is that Grandview got a permanently different pedestrian environment out of a project that took longer than anyone wanted, for a reason nobody could have predicted, and that the next visible change in the district, the Hempel and Jester Concepts redevelopment, is still a plan on paper rather than dirt in the ground as of this writing.

If you live near Vernon Avenue, the ten-foot sidewalks and the removed ramps are yours to use starting now. If you're watching the 50th and Highway 100 corner for what comes next, the groundbreaking that developers targeted for summer 2026 is the thing to confirm, since that summer has now passed, before you assume it's underway.

Grandview has spent two construction seasons being a district in progress. This is the first one where it isn't.